Canadian Pacific Railway (CPR) is removing the siding track at 5th Ave, Centre Ave and River Ave crossings.
This work is scheduled between May 3-10. Crossings will be closed one at time, for two days each to complete the work.
Traffic controls and signage will be in place during these closures.
Schedule:
Work will start at 5th Ave at 0700h on May 3; Centre and then River will follow later in the week, in that order.
Please see tentative schedule below, dates may be adjusted as a result of work progress.
May 3 & 4: 5th Ave crossing closed
May 5 & 6: Centre Ave crossing closed
May 7 & 8: River Ave crossing closed
May 9 & 10: extra days in place if work is postponed or delayed